1. Clearance and Working Space while planning Piping for Shell and Tube Exchangers
Why is it essential to maintain clearance and working space around both ends while planning Piping for Shell and Tube Exchangers?
Explanation: Adequate clearance and working space around both ends of the heat exchanger facilitate maintenance activities by ensuring unobstructed removal of channel heads, shell covers, and tube bundles.
2. Piping Elevation
What is the recommended minimum clearance for elevating the piping from grade above the ground level?
Explanation: The recommended minimum clearance for elevating the piping from grade is 300mm above the ground level.
3. Channel Head Removal
How can channel head removal be simplified according to the provided information?
Explanation: Piping connected to channel head nozzles should be equipped with break flanges to simplify channel head removal.
4. Steam Line Arrangement
What is the recommended position for steam lines connecting to a header in the yard?
Explanation: Steam lines connecting to a header in the yard should be positioned on either side of the exchanger centerline without increasing pipe length.
5. Cooling-Water Line Arrangement
What is the recommended routing for underground cooling-water lines?
Explanation: For underground cooling-water lines, route them directly beneath the aligned channel nozzles of all coolers.
6. Valve and Instrument Accessibility
What should be considered when designing the piping arrangement around heat exchangers regarding valve handwheels?
Explanation: Valve handwheel and instrument accessibility should be considered by ensuring valve handwheels are accessible from grade and convenient accessways.
7. Accessways for Manifolds
How can accessways be utilized in the piping arrangement around heat exchangers?
Explanation: Accessways should be utilized for arranging manifolds, control valves, and instruments to ensure easy accessibility during maintenance.
Short Article on Piping for Shell and Tube Exchangers
Heat Exchanger Piping for Shell and Tube Exchangers
Clearance and Working Space
- Allocate adequate clearance and working space around both ends of the heat exchanger to facilitate maintenance activities.
- Maintain these working spaces clear of obstructions, such as piping and accessories, to ensure unobstructed removal of channel heads, shell covers, and tube bundles.
- Utilize the free space at the side of horizontal shells for placing control stations.
Piping Elevation
- Elevate the piping from grade to provide a minimum clearance of 300mm above the ground level.
Channel Head Removal
- Equip piping connected to channel head nozzles with break flanges to simplify channel head removal.
Steam Line Arrangement
- Position steam lines connecting to a header in the yard on either side of the exchanger centerline without increasing pipe length.
Cooling-Water Line Arrangement
- For underground cooling-water lines, route them directly beneath the aligned channel nozzles of all coolers.
Valve and Instrument Accessibility
- Consider valve handwheel and instrument accessibility when designing the piping arrangement around heat exchangers.
- Ensure that valve handwheels are accessible from grade and from a convenient accessway.
- Utilize these accessways for arranging manifolds, control valves, and instruments.
Table of Contents
Don’t miss the Course on Effective Isometrics Management: Check Now
Enrollment Link
Recommended courses (Published on EPCLand)
- Complete Course on Piping Engineering
- Basics of Piping Engineering
- Piping Layout Engineering
- Piping Material Engineering
- Piping Stress Analysis
- Material Requisitions
- Piping Material Specifications
- Valve Material Specifications
- Plant Design & Layouts-OISD 118
- Isometric Management
Library of Technical Articles
Don’t miss out the collection of 15+ articles on following topics:
- Basics of Oil and Gas Industry
- Valves
- Testing
- Tank
- Piping Bulk Items
- Pipe
- Metallurgy
- Piping Materials
- Layout
- Instrumentation
- Heat Exchanger
- Type of Contracts
- Codes and Standards
- ASTM Standards
- Articles on Piping Specialty Items
Video details of Complete Course on Piping Engineering
Why Enroll in the EPCLand
Proven Track Record– PTR
Activities & Achievements before launching EPCLand
- Published more than 50+ short courses
- 3000+ Enrolments
- More than 3,500,00 Minutes of watch hours in the last 2 years
- 4000+ Students in 100+ Countries
- Rating of 4+ out of 5
- 1000+ YouTube Videos
- 8K+ Subscribers
What Students will Learn
- Codes & Standards of the Energy Sector
- Piping Material Engineering
- Piping Layout Engineering
- Stress Analysis
Interesting facts
- All the published courses have been developed by Industry Experts with more than 2 decades of experience
- Content is based on Practical experience and real-time problems.
- Content is designed and organized in such a manner that it can be easily grabbed.
- Complete website, Blogs and Quiz sections are Planned, Designed and published by myself (About me: Atul Singla)
- Complete flexibility of Time & Location, Students can access the content from anywhere & anytime
- Moreover, once enrolled, the content can be access as many times as you want, which helps in understand the fundamentals in a better way.
Conclusion
In conclusion, our courses are meticulously crafted by industry experts with over two decades of hands-on experience. The content is rooted in practical knowledge, addressing real-time problems. The material is thoughtfully designed and organized for easy comprehension. Every aspect, from the website to blogs and quizzes, has been planned, designed, and executed by Atul Singla, ensuring a comprehensive and seamless learning experience. With the flexibility of accessing the content at any time and from any location, students have the freedom to learn on their terms. Furthermore, enrollment grants unlimited access, allowing learners to revisit the material as often as needed, fostering a deep understanding of the fundamentals.